Decision:
RESOLVED that:-
Planning Permission be GRANTED, subject to conditions.
Minutes:
Demolition of existing single storey workshop building and erection of a pair of three-storey plus basement semi-detached houses (comprising 1 x 4 bed house and 1 x 3 bedroom house) with provision of rear garden space.
7.1 The Planning Officer introduced the report, as set out in the agenda.
7.2 David Warrilow and Clive Rush spoke in objection to the scheme, their comments are summarised as follows:
§ Pleased to see that revisions had been made to the original application, including the removal of the parking.
§ Do not object to the warehouse being developed, they just had a couple of objections.
§ There was still some overlooking into the bedroom window of the neighbouring property.
§ The amount of sunlight had been reduced due to the height of the proposed building.
§ They want the party wall to remain in situ.
§ Issue over the right of entry to the private road which had been previously given to number 70 but not 70A. This would need to be resolved.
7.3 The applicant spoke in support of the scheme, her comments are summarised as follows:
§ Assured the Committee that she was in possession of all the deeds regarding the right of entry issue.
§ Seven revisions had been made to the original plans, including the inclusion of the party wall.
§ Complex site and done their best to build the development to a very high standard.
§ The height of the proposed development was in line with the neighbouring properties.
7.4 The Chair wished to clarify the issue of overlooking into the objector’s property and the Planning Officer believed that the development would not have a negative impact on the property.
7.5 Reference was made to the party wall and the applicant confirmed that the party wall would remain as a structured wall. The Planning Officer added that condition 7 of the recommendation referred to the retention of the party wall.
Unanimously RESOLVED that:-
Planning Permission be GRANTED, subject to imposition of the following conditions:-
1. SCBN1 –Commencement within three years
The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this permission.
REASON: In order to comply with the provisions of Section 91(1) of the Town and Country Planning Act 1990 as amended.
2. SCB0 – Development only in accordance with submitted plans
The Development hereby permitted shall only be carried out and completed strictly in accordance with the submitted plans hereby approved and any subsequent approval of details.
REASON: To ensure that the development hereby permitted is carried out in full accordance with the plans hereby approved.
3. SCM2 - Materials to be approved
Full details, including samples, of the materials to
be used on the external surfaces of the building, including
glazing, shall be submitted to and approved by the Local Planning
Authority, in writing, before any work commences on
site. The development shall
not be carried out otherwise than in accordance with the details
thus approved.
REASON: To ensure that the external appearance of the building is
satisfactory and does not detract from the character and visual
amenity of the area.
4. SCM7 - Details to be approved
Detailed drawings/full particulars of the proposed development showing the matters set out below must be submitted to and approved by the Local Planning Authority, in writing, before any work is commenced.
The development shall not be carried out otherwise than in accordance with the details thus approved:
- Windows and Doors
REASON: To ensure that the external
appearance of the building is satisfactory and does not detract
from the character and visual amenity of the area.
5. SCM9 - No extraneous pipework
No soil stacks, soil vent pipes, flues, ductwork or any other pipework shall be fixed to the (street) elevations of the building other than as shown on the drawings hereby approved.
REASON: To ensure that the external appearance of the building is
satisfactory and does not detract from the character and visual
amenity of the area.
6. SCR2 – Details of refuse storage enclosure
Details of dustbin enclosures showing the design, external appearance and location thereof, shall be submitted to and approved by the Local Planning Authority, in writing, before construction commences. The development shall not be carried out otherwise than in accordance with the details thus approved.
REASON: To ensure there is adequate provision for dustbin and
recycling facilities for the development in the interests of the
appearance and amenity of the area.
7. Non-standard – Rear Wall to be retained
The existing building
wall located on, or near, the boundary with No.2 Cobble Mews shall
be protected and retained throughout all stages of development and
following completion of the development.
REASON: To protect the living conditions of neighbouring
properties
8. SCG 6 - Restriction of Permitted Development Rights
Notwithstanding the provisions of the
Town and Country Planning General Development Order 1988 (or any
Order revoking and re-enacting that Order), planning permission
shall be required in respect of development falling within Part 1
to the second schedule to that Order.
REASON: To safeguard the amenities of local
residents and to protect the character and appearance of the
area.
9. SCG10 – Soil Contamination
No development shall take place until details and results of a soil contamination survey of the site and details of remedial measures proposed to treat/eradicate any contamination found have been submitted by the applicant and approved by the Local Planning Authority in writing. The survey shall be carried out by a suitably qualified person or body to be agreed by the Council. The development shall not take place otherwise than in accordance with the details so approved.
REASON: To ensure that the condition of the site is suitable for the development proposed and to ensure a reasonable quality of natural environment, in order to safeguard future occupiers and users of the site.
INFORMATIVES
The following Informatives should be added:
SI.1 Building Control
SI.2 Work Affecting Public Highway
SI.3 Sanitary, Ventilation
and Drainage Arrangements
SI.6 Control of Pollution (Clean Air, Noise, etc.)
SI.7 Hours of Building Works
Sl.24 Naming and Numbering
SI.27 Regulatory Reform (Fire Safety) Order 2005
SI.28 Refuse Storage and Disposal Arrangements
SI.19 Health and Safety at Work Act
NSI.1 All materials submitted
pursuant to the discharge of conditions 3 and 4 of this granting of
full planning permission ('materials to be approved') should be
supplied and delivered at the same time in a container clearly
marked with the address of the application site, reference to the
application number 2008/1586, and accompanied by coloured copies of
relevant elevational drawings, to which
each material sample should be clearly referenced and labelled
accordingly. Full specifications detailing each material's
manufacturer and colour (as per manufacturer's description/name
thereof) should also be submitted at the same time.
REASONS FOR APPROVAL
The following policies saved in the Hackney Unitary Development Plan (1995) are relevant to the approved development/use and were considered by this Council in reaching the decision to grant planning permission: EQ1 - Development Requirements; EQ1 - Development Requirements; EQ43 - Development of Contaminated Land; EQ48 - Designing out Crime; and HO3 - Other Sites for Housing.
The following policies in the London Plan (2008) are relevant to the approved development/use and were considered by this Council in reaching the decision to grant planning permission: 3A.2 - Density Matrix; 4B.1 - Design principles for a compact city; 4B.4 - Enhancing the quality of the public realm.
Supporting documents: