Issue - meetings

G. Benabo Court, Ferncliffe Road

Meeting: 03/09/2008 - Planning Sub-Committee (Item 18)

18 G. Benabo Court, Ferncliff Road, London, E8 2JL: 2007/2976 pdf icon PDF 130 KB

Decision:

 

    RESOLVED that:

 

Permission (ref. 2007/2976 – Benabo Court) be GRANTED, subject to conditions.

Minutes:

Erection of a four storey building fronting Sandringham Road to provide 8 x 2 bed units.  Internal alterations involving conversion of offices to new 1 bed sheltered flat and conversion wardens flat to 2, one bed sheltered flats relocation of existing sheltered communal lounge and new conservatory.

 

g.1    The Planning Officer introduced the report as set out in the report. 

 

g.2    The Chair raised the issue of fly parking, as he was concerned that the landscaping would be used as parking.  

 

g.3  Following a query regarding the high fencing on the corner of Ferncliff Road, it was confirmed that this fencing would be applied to all of the boundary walls.

 

Councillor Smith abstained from the vote.

 

    RESOLVED that:

 

Permission (ref. 2007/2976 – Benabo Court) be GRANTED, subject to the following conditions:

 

1.  SCB0 – Development in accordance with plans

  The development hereby permitted shall only be carried out and completed strictly in accordance with the submitted plans hereby approved and any subsequent approval of details.

 

  REASON: To ensure that the development hereby permitted is carried out in full accordance with the plans hereby approved.

 

  2.  SCB1 – Commencement within three years

The development hereby permitted must be begun not later than three years after the date of this permission.

 

REASON: In order to comply with the provisions of Section 91(1) of the Town and Country Planning Act 1990 as amended.

 

  3.  SCM6 – Materials to be approved (entire site)

  Details, including samples, of materials to be used on the external surfaces of the building, boundary walls and ground surfaces shall be submitted to and approved by the Local Planning Authority, in writing, before any work commences on site. The development shall not be carried out otherwise than in accordance with the details thus approved.

 

  REASON: To ensure that the external appearance of the building is satisfactory and does not detract from the character and visual amenity of the area.

 

 

  4.  SCM7 – Details to be approved

Detailed drawings/full particulars of the proposed development  showing the matters set out below must be submitted to and approved by the Local Planning Authority, in writing, before any work is commenced. The development shall not be carried out otherwise than in accordance with the details thus approved.

·  Balustrade details 

·  Timber cladding details 

·  Paving details

 

REASON: To ensure that the external appearance of the building is satisfactory and does not detract from the character and visual amenity of the area.

 

  5.  SCM9 – No extraneous pipework

No soil stacks, soil vent pipes, flues, ductwork or any other pipework shall be fixed to the (street) elevations of the building other than as shown on the drawings hereby approved.

 

REASON: To ensure that the external appearance of the building is satisfactory and does not detract from the character and visual amenity of the area.

 

  6.  SCT2 – Provision of landscaping as approved

The landscaping hereby approved as part of the development shall be carried out within a period of twelve months from the date on  ...  view the full minutes text for item 18